| DATE
| ACTIVITY
|
| Jan. 1 2003
| Arrival to Puno or La Paz.
|
| Jan. 2 2003
| Transport to the stations.
Pilot balloon launching starts in some stations. There were equipment problems.
|
| Jan. 3 2003
|
All stations were set up, ending with Conima.
Generalized surface wind and sky observation starts. Temperature measurements start at Bolivia.
Pilot balloon launching starts at 00UTC on the 4th where problems were initially found.
|
| Jan. 4 2003
|
Regular pilot balloon launching.
Regular temperature measuring.
|
| Jan. 4-8 2003
| Continuity on measurements.
Starts installation of max-min thermometers and measurements.
Starts installation of raingauges on Taquile, Soto and Amantani.
|
| Jan. 9 2003
| Station cleaning.
Participants are taken to Puno or La Paz.
Dinner at "El Trabuco" restaurant.
|
| Jan. 10 2003
| Participants taken to La Paz, Bolivia.
|